Navarro
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Hill County. First named in the release with data as of February 1, 2026.
Hillcounty as printed
345kV
LSTutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Hill, TX: ERCOT queue, 23 active of 27. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| LST_SamSwitch_Resiliency_(GTC)_Project This project loops Helix to Navarro Circuit into LST Sam Switch station ERCOT project 102401 · RPG 25RPG031 |
LST Tier 3 |
Planned Completed tab |
345 | Jun 2026 actual 2026-06 |
Helix to Navarro Hill County |
Helix, Navarro |
| LST_Liberty_To_Navarro_New_345kV_Line_BZ_LLI Build new 345 kV single ckt line connecting LST Liberty Station to LST Navarro Station with 5000 Amps minimum ratings. ERCOT project 110232 |
LST Tier 2 |
Conceptual Future tab |
345 | Dec 2030 | Navarro to Liberty Hill / Navarro County |
Navarro, Liberty |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 102401 | Moved between tabs | Current-year planned → Completed |
| July 13, 2026 | 110232 | First listed | on the Future tab |
| February 1, 2026 | 102401 | First listed | on the Current-year planned tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.