Substation Scout

Weslaco

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Hidalgo County. First named in the release with data as of February 1, 2023.

Hidalgocounty as printed
138kV
AEP TCC, STECutility
2projects listed

Also printed as: Weslaco Switch

A HIFLD substation record has the same name and county: WESLACO (HIDALGO County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Hidalgo, TX: ERCOT queue, 25 active of 31. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Weslaco Switch: 138 kV Breaker Replacement
Replace 138 kV breakers at the Weslaco Switch 138 kV station
ERCOT project 103419 · utility no. TP2026026
AEP TCC
Tier 4
Planned
Future tab
138 Dec 2028 Weslaco Switch
Hidalgo County
Weslaco Switch
Upgrade Heidelberg to AEP Weslaco line
Upgrade Heidelberg to STEC WESLACO and STEC WESLACO to AEP Weslaco lines to be 478MVA capable
ERCOT project 71928
STEC
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Heidelberg to Weslaco
Hidalgo County
Heidelberg, Weslaco

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026103419First listedon the Future tab
February 1, 202671928Moved between tabsFuture → Current-year planned
October 1, 202571928Projected in-service dateMay 2026 → Dec 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first