North McAllen
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Hidalgo County. First named in the release with data as of June 1, 2016.
A HIFLD substation record has the same name and county: NORTH MCALLEN (HIDALGO County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Hidalgo, TX: ERCOT queue, 25 active of 31. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| North Edinburg to North McAllen: Rebuild 138 kV line ERCOT project 104151 · utility no. TA2021190 |
AEP TCC Tier 2 |
Planned Future tab |
138 | Jan 2031 | North Edinburg to North McAllen Hidalgo County |
North Edinburg, North McAllen |
| North McAllen: Construct New 138 kV Terminal Interconnect Carambola BESS to the North McAllen 138 kV station ERCOT project 80482 |
AEP TCC Tier 4 |
In-Service Current-year planned tab |
138 | Dec 2026 actual 2026-03 |
North McAllen Hidalgo County |
North McAllen |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 104151 | Projected in-service date | Jan 2032 → Jan 2031 |
| October 1, 2026 | 80482 | Status as reported | Planned → In-Service |
| June 1, 2026 | 104151 | First listed | on the Future tab |
| June 1, 2026 | 80482 | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2026 | 80482 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 80482 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 80482 | Projected in-service date | Nov 2025 → May 2026 |
| June 1, 2025 | 80482 | Moved between tabs | Future → Current-year planned |
| June 1, 2024 | 80482 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.