Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Hidalgo County. First named in the release with data as of June 1, 2024.

Hidalgocounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Hidalgo, TX: ERCOT queue, 25 active of 31. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Closner: Construct New 138 kV Terminal
Interconnect Gunnar BESS to the Closner 138 kV station
ERCOT project 80484
AEP TCC
Tier 4
Planned
Current-year planned tab
138 Nov 2026 Closner
Hidalgo County
Closner

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202680484Projected in-service dateJun 2026 → Nov 2026
February 1, 202680484Moved between tabsFuture → Current-year planned
October 1, 202580484Moved between tabsCurrent-year planned → Future
October 1, 202580484Projected in-service dateNov 2025 → Jun 2026
June 1, 202580484Moved between tabsFuture → Current-year planned
February 1, 202580484Projected in-service dateOct 2025 → Nov 2025
June 1, 202480484First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first