Buddy Owens
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Hidalgo County. First named in the release with data as of October 1, 2023.
Described as new. The quoted wording calls this substation new. “Buddy Owens: Build new 138 kV Substation” — project 73423 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Hidalgo, TX: ERCOT queue, 25 active of 31. Same county, not the same substation.
Location
Hidalgo County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: TPIT 73423 status is Conceptual (ISD 2027-11).
Sources: ERCOT TPIT, project 73423 (release 39, 2026-10-01), sheet FutureTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Buddy Owens: Build new 138 kV Substation Build new 138 kV substation on Key Switch to North McAllen 138 kV line ERCOT project 73423 |
AEP TCC Tier 4 |
Conceptual Future tab |
138 | Nov 2027 | Buddy Owens Hidalgo County |
Buddy Owens |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 73423 | Projected in-service date | May 2026 → Nov 2027 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.