Agrios

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Hidalgo County. First named in the release with data as of October 1, 2025.

Hidalgocounty as printed
345kV
AEP TCCutility
1projects listed

Described as new. The quoted wording calls this substation new. “Agrios: Construct New 345 kV Station” — project 98737 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Hidalgo, TX: ERCOT queue, 25 active of 31. Same county, not the same substation.

Location

Hidalgo County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Sources: ERCOT TPIT, project 98737 (release 39, 2026-10-01), sheet FutureTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Agrios: Construct New 345 kV Station
Interconnect Grapefruit Solar to the new Agrios 345 kV station on the North Edinburg to Reforzar 345 kV line
ERCOT project 98737 · utility no. TP2025218
AEP TCC
Tier 4
Planned
Future tab
345 Apr 2028 Agrios
Hidalgo County
Agrios

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202598737First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.