Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Haskell County. First named in the release with data as of October 1, 2021.

Haskellcounty as printed
345kV
ETT/AEP TNC/ETTutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Haskell, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Pendulo: Build New 345 kV terminal
Interconnect Inertia Solar and BESS 2 to the Pendulo 345 kV Station on the Clear Crossing to Smoky Hill line
ERCOT project 76131
ETT/AEP TNC/ETT
Tier 4
Planned
Future tab
345 Oct 2028 Pendulo
Haskell County
Pendulo
Pendulo: Construct New 345 kV Terminal
Interconnect Rubicon Alpha Wind to the Pendulo 345 kV station
ERCOT project 86800
ETT/AEP TNC/ETT
Tier 4
Planned
Future tab
345 Jan 2027 Pendulo
Haskell County
Pendulo

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202576131Projected in-service dateMay 2027 → Oct 2028
October 1, 202476131Projected in-service dateOct 2026 → May 2027
October 1, 202486800First listedon the Future tab
June 1, 202476131Projected in-service dateMay 2025 → Oct 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.