Substation Scout

Kilby

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Haskell County. First named in the release with data as of June 1, 2024.

Haskellcounty as printed
345kV
ETT, ETT/AEP TNCutility
2projects listed

Described as new. The quoted wording calls this substation new. “Kilby: Construct New 345 kV Station” — project 80508 title, as the utility reported it

Reported complete. Project 80508 is on the Completed tab (actual in-service 2026-01), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Haskell, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.

Location

Haskell County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: Already in service: TPIT 80508 is on the Completed tab, 'IN-SERVICE', actual 2026-01.

Sources: ERCOT TPIT, projects 80508, 99728 (release 39, 2026-10-01), sheets CompletedTPIT100126NoCost, FutureTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Kilby: Construct New 345 kV Station
Interconnect Quantum Solar to the new Kilby 345 kV station on the Clear Crossing to Pendulo 345 kV line
ERCOT project 80508
ETT
Tier 4
In-Service
Completed tab
345 Jan 2026
actual 2026-01
Kilby
Haskell County
Kilby
Kilby: Expand 345 kV Station
Interconnect Briggs Solar and BESS to the existing Kilby 345 kV station
ERCOT project 99728
ETT/AEP TNC
Tier 4
Planned
Future tab
345 May 2027 Kilby
Haskell County
Kilby

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202699728Projected in-service dateNov 2027 → May 2027
June 1, 202680508Moved between tabsCurrent-year planned → Completed
June 1, 202680508Status as reportedPlanned → In-Service
February 1, 202680508Moved between tabsFuture → Current-year planned
February 1, 202680508Projected in-service dateMar 2026 → Jan 2026
October 1, 202580508Moved between tabsCurrent-year planned → Future
October 1, 202580508Projected in-service dateNov 2025 → Mar 2026
October 1, 202599728First listedon the Future tab
June 1, 202580508Moved between tabsFuture → Current-year planned
June 1, 202480508First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.