Clear Crossing

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Haskell County. First named in the release with data as of February 1, 2016.

Haskellcounty as printed
345kV
AEP TNC/ETT, ETT/AEP TNCutility
3projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345 kV Station” — project 103459, as the utility reported it

A project here also describes a named load connected: “Interconnect the Google Ranger load to the existing Clear Crossing 345 kV station” (project 103459)

A HIFLD substation record has the same name and county: CLEAR CROSSING (HASKELL County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Haskell, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Clear Crossing: Expand 345 kV Station
Interconnect the Google Ranger load to the existing Clear Crossing 345 kV station
ERCOT project 103459 · utility no. TP2025843
ETT/AEP TNC
Tier 4
Planned
Future tab
345 Jun 2028 Clear Crossing
Haskell County
Clear Crossing
Clear Crossing: Install New 345 kV Capacitor Bank
Install a new capacitor bank at the Clear Crossing 345 kV station
ERCOT project 110055 · utility no. TP2026076
AEP TNC/ETT
Tier 4
Planned
Future tab
345 Dec 2027 Clear Crossing
Haskell County
Clear Crossing
Clear Crossing: Build 345 kV terminal
Interconnect HODL Ranch II at Clear Crossing 345 kV station
ERCOT project 63956 · utility no. 1884
ETT/AEP TNC
Tier 4
In-Service
Completed tab
345 Jun 2026
actual 2026-06
Clear Crossing to HODL Ranch II
Haskell County
Clear Crossing, HODL Ranch II

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110055First listedon the Future tab
July 13, 202663956Moved between tabsCurrent-year planned → Completed
July 13, 202663956Status as reportedUnder Construction → In-Service
June 1, 2026103459First listedon the Future tab
February 1, 202663956Moved between tabsFuture → Current-year planned
October 1, 202563956Status as reportedPlanned → Under Construction
February 1, 202563956Projected in-service dateDec 2024 → Jun 2026
June 1, 202463956Projected in-service dateMar 2024 → Dec 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.