Red Rock
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Hall County. First named in the release with data as of July 13, 2026.
Hallcounty as printed
345kV
CTTutility
4projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Hall, TX: SPP queue, 0 active of 2. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| CTT Red Rock station/Cross Expansion Will replace CTT Cross Expansion PMCR. Adds total of 225 MVar cap banks, removes series capacitors. ERCOT project 110156 |
CTT Tier 4 |
Conceptual Future tab |
345 | Nov 2027 | No terminals printed Hall County |
Red Rock |
| Add double circuit line from CTT Red Rock to Oncor Ogallala ERCOT project 110304 |
CTT Tier 3 |
Conceptual Future tab |
345 | Apr 2028 | CTT Red Rock to Oncor Ogallala Hall / Castro County |
Red Rock, Ogallala |
| Add CTT Comanchero station on Tule Canyon - Red Rock (Cross) dbl ckt ERCOT project 110577 |
CTT Tier 4 |
Conceptual Future tab |
345 | Jul 2028 | Tule Canyon to Red Rock Briscoe / Hall County |
Tule Canyon, Red Rock |
| Add dbl ckt between CTT Red Rock and Edith Clark ERCOT project 110595 |
CTT Tier 3 |
Conceptual Future tab |
345 | Jul 2028 | Red Rock to Edith Clark Hall / Foard County |
Red Rock, Edith Clark |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110156 | First listed | on the Future tab |
| July 13, 2026 | 110304 | First listed | on the Future tab |
| July 13, 2026 | 110577 | First listed | on the Future tab |
| July 13, 2026 | 110595 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.