Substation Scout

Prairieland

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Glasscock County. First named in the release with data as of October 1, 2023.

Glasscockcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Glasscock, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Prairieland 345/138 kV Switch and 138 kV Line
Establish Prairieland 345/138 kV Switch and Prairieland – Quartz Sand 138 kV Line
ERCOT project 76705 · utility no. R8632 · RPG 24RPG006
ONCOR
Tier 2
Planned
Completed tab
345 Sep 2025
actual 2025-12
Prairieland to Quartz Sand
Glasscock County
Prairieland, Quartz Sand

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202676705Moved between tabsCurrent-year planned → Completed
June 1, 202576705Moved between tabsFuture → Current-year planned
February 1, 202576705Projected in-service dateMay 2025 → Sep 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.