Substation Scout

Hog Mountain POD

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Glasscock County. First named in the release with data as of October 1, 2023.

Glasscockcounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Glasscock, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Hog Mountain 138 kV POD
Add Hog Mountain 138 kV POD
ERCOT project 76686 · utility no. R8673 R8791
ONCOR
Tier 4
Planned
Completed tab
138 Sep 2025
actual 2025-12
Quartz Sand to Hog Mountain POD
Glasscock County
Quartz Sand, Hog Mountain POD

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202676686Moved between tabsCurrent-year planned → Completed
June 1, 202576686Moved between tabsFuture → Current-year planned
June 1, 202576686Projected in-service dateApr 2025 → Sep 2025
February 1, 202576686Moved between tabsCompleted → Future
February 1, 202576686Projected in-service dateApr 2024 → Apr 2025
October 1, 202476686Moved between tabsFuture → Completed
October 1, 202476686Projected in-service dateDec 2024 → Apr 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this