Substation Scout

Cascabel

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Fisher County. First named in the release with data as of July 13, 2026.

Fishercounty as printed
345kV
AEP TNC/ETTutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Fisher, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Cesium: Install New 345 kV Capacitor Bank
Install a new capacitor bank at the Cesium 345 kV station
ERCOT project 110419
AEP TNC/ETT
Tier 4
Conceptual
Future tab
345 Feb 2029 Cascabel
Fisher County
Cascabel

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110419First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first