Sterrett Switch
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Ellis County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
Also printed as: Sterrett
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Ellis, TX: ERCOT queue, 26 active of 30. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Ennis West Switch – Sterrett Switch 138kV Line Upgrade Upgrade Ennis West Switch – Sterrett Switch 138kV Line ERCOT project 105316 · utility no. M4200 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
138 | May 2027 | Ennis West Switch to Sterrett Switch Ellis County |
Ennis West Switch, Sterrett Switch |
| Sterrett Switch – MidlothianTXI 138kV_Line_Upgrade Upgrade Sterrett Switch – MidlothianTXI 138kV Line Upgrade ERCOT project 105330 · utility no. M4349 · RTP 25RPT004 |
ONCOR Tier 1 |
Planned Future tab |
138 | Dec 2027 | Sterrett Switch to Midlothian TXI Ellis County |
Sterrett Switch, Midlothian TXI |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Sterrett - Sardis 138 kV line Upgrade existing 138 kV line ERCOT project 07TPIT0069 · utility no. M361-E |
ONCOR Tier 4 |
Conceptual Cancelled tab |
138 | May 2025 | Sterrett to Sardis Ellis County |
Sterrett, Sardis |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 105316 | First listed | on the Future tab |
| June 1, 2026 | 105330 | First listed | on the Future tab |
| October 1, 2024 | 07TPIT0069 | First listed | on the Cancelled tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.