South Watermill
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Ellis County. First named in the release with data as of June 1, 2026.
Elliscounty as printed
765kV
ONCORutility
4projects listed
Also printed as: South Watermill 765 kV Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Ellis, TX: ERCOT queue, 26 active of 30. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| South Watermill 765 kV Switch Establish South Watermill 765 kV Switch ERCOT project 105888 · utility no. M4478, M4460, M4459 · RPG 25RPG025 |
ONCOR Tier 1 |
Planned Future tab |
765 | Dec 2030 | South Watermill 765 kV Switch Ellis County |
South Watermill 765 kV Switch |
| South Watermill - Bell East 765 kV Line Establish South Watermill - Bell East 765 kV Line ERCOT project 112322 · utility no. M4458 · RPG 25RPG025 |
ONCOR Tier 1 |
Planned Future tab |
765 | Jun 2032 | South Watermill to Bell East Ellis / Bell County |
South Watermill, Bell East |
| South Watermill - Dinosaur 765 kV Line Establish South Watermill - Dinosaur 765 kV Line ERCOT project 112324 · utility no. M4460 · RPG 25RPG025 |
ONCOR Tier 1 |
Planned Future tab |
765 | Dec 2030 | South Watermill to Dinosaur Ellis / Somervell County |
South Watermill, Dinosaur |
| South Watermill - East Watermill 765 kV Line Establish South Watermill - East Watermill 765 kV Line ERCOT project 112326 · utility no. M4478 · RPG 25RPG025 |
ONCOR Tier 1 |
Planned Future tab |
765 | Dec 2030 | South Watermill to East Watermill Ellis County |
South Watermill, East Watermill |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 105888 | Projected in-service date | May 2032 → Dec 2030 |
| October 1, 2026 | 112322 | First listed | on the Future tab |
| October 1, 2026 | 112324 | First listed | on the Future tab |
| October 1, 2026 | 112326 | First listed | on the Future tab |
| June 1, 2026 | 105888 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.