Ramhorn

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Denton County. First named in the release with data as of June 1, 2025.

Dentoncounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Denton, TX: ERCOT queue, 1 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Ramhorn 138kV Switch
Establish Ramhorn 138kV Switch and Ramhorn -Dunham 138 kV Line
ERCOT project 76312 · utility no. M5007
ONCOR
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Ramhorn to Dunham
Denton County
Ramhorn, Dunham

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202676312Projected in-service dateMay 2026 → Dec 2026
June 1, 202676312Moved between tabsFuture → Current-year planned
June 1, 202676312Projected in-service dateMay 2027 → May 2026
February 1, 202676312Projected in-service dateDec 2026 → May 2027
February 1, 202576312Projected in-service dateMay 2026 → Dec 2026
October 1, 202476312Projected in-service dateMay 2027 → May 2026
June 1, 202476312First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.