Wilmer
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Dallas County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
Also printed as: Wilmer Switch
A HIFLD substation record has the same name and county: WILMER (DALLAS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Wilmer Switch – Navarro Switch (Lonestar) 345 kV Double-Circuit Line Establish Wilmer Switch – Navarro Switch (Lonestar) 345 kV Double-Circuit Line ERCOT project 105759 · utility no. M4446 · RPG 25RPG004 · RTP 2024-NC63 |
ONCOR Tier 1 |
Planned Future tab |
345 | May 2032 | Wilmer Switch to Navarro Switch Dallas / Navarro County |
Wilmer Switch, Navarro Switch |
| Wilmer 345kV Statcom Establish Wilmer 345kV Statcom ERCOT project 105838 · utility no. M5016 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2029 | Wilmer Dallas County |
Wilmer |
| Greene Switch - Wilmer Switch 345 kV Double-Circuit Line Establish Greene Switch - Wilmer Switch 345 kV Double-Circuit Line ERCOT project 110377 · utility no. M4364 · RPG 25RPG042 · RTP 2024-NC86 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2028 | Greene Switch to Wilmer Switch Dallas County |
Greene Switch, Wilmer Switch |
| Wilmer 345/138 kV Switch Establish Wilmer 345/138 kV Switch ERCOT project 78357 · utility no. M4369 M4371 M4372 · RPG 24RPG022 |
ONCOR Tier 1 |
In-Service Completed tab |
345 | Mar 2026 actual 2026-06 |
Wilmer Dallas County |
Wilmer |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Waxahachie-Waxahachie OCF 69 kV Line Rebuild Rebuild the existing Waxahachie-Waxahachie OCF 69 kV Line ERCOT project 71136 · utility no. M4339 |
ONCOR Tier 4 |
Planned Cancelled tab |
69 | Jul 2025 | Wilmer to Waxahachie Dallas / Ellis County |
Wilmer, Waxahachie |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 78357 | Moved between tabs | Current-year planned → Completed |
| October 1, 2026 | 78357 | Status as reported | Planned → In-Service |
| July 13, 2026 | 110377 | First listed | on the Future tab |
| June 1, 2026 | 105759 | First listed | on the Future tab |
| June 1, 2026 | 105838 | First listed | on the Future tab |
| February 1, 2026 | 71136 | First listed | on the Cancelled tab |
| February 1, 2026 | 78357 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 78357 | Projected in-service date | Dec 2025 → Mar 2026 |
| October 1, 2024 | 71136 | No longer listed | future |
| October 1, 2024 | 78357 | Projected in-service date | May 2026 → Dec 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.