Substation Scout

West Levee

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of June 1, 2015.

Dallascounty as printed
138kV
ONCORutility
1projects listed

A HIFLD substation record has the same name and county: WEST LEVEE (DALLAS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Cedar Crest - Dealey - West Levee 138 kV Line
Upgrade the existing 138 kV Line
ERCOT project 66188 · utility no. M4212
ONCOR
Tier 4
In-Service
Completed tab
138 Mar 2026
actual 2026-05
Ceadr Crest to West Levee
Dallas County
Ceadr Crest, West Levee

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202666188Moved between tabsCurrent-year planned → Completed
October 1, 202666188Status as reportedPlanned → In-Service
February 1, 202666188Moved between tabsFuture → Current-year planned
February 1, 202666188Projected in-service dateDec 2026 → Mar 2026
October 1, 202566188Moved between tabsCurrent-year planned → Future
October 1, 202566188Projected in-service dateDec 2025 → Dec 2026
June 1, 202566188Moved between tabsFuture → Current-year planned
February 1, 202566188Projected in-service dateMay 2025 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first