Sunrise Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of October 1, 2026.

Dallascounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Sunrise 138 kV Switch
Establish Sunrise 138 kV Switch
ERCOT project 111702 · utility no. M5018
ONCOR
Tier 4
Planned
Future tab
138 May 2029 Sunrise Switch
Dallas County
Sunrise Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026111702First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.