Substation Scout

Kirkland

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of October 1, 2025.

Dallascounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Kirkland 138 kV Capacitor Bank
ERCOT project 99941 · utility no. M4022
ONCOR
Tier 4
Planned
Future tab
138 May 2027 Kirkland
Dallas County
Kirkland

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699941Moved between tabsCurrent-year planned → Future
October 1, 202699941Projected in-service dateDec 2026 → May 2027
February 1, 202699941Moved between tabsFuture → Current-year planned
February 1, 202699941Projected in-service dateDec 2030 → Dec 2026
October 1, 202599941First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first