Substation Scout

Cypress Waters

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of October 1, 2023.

Dallascounty as printed
138kV
ONCORutility
2projects listed

Also printed as: Cypress Waters Switch

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Vineyard Switch-Cypress Waters Switch 138 kV Line
Construct a new 138 kV circuit from Vineyard to Cypress Waters
ERCOT project 64239 · utility no. M5320 · RPG 24RPG019
ONCOR
Tier 3
Planned
Current-year planned tab
138 Dec 2026 Cypress Waters Switch to Vineyard Switch
Dallas / Tarrant County
Cypress Waters Switch, Vineyard Switch
Line Termination at Cypress Waters
Vineyard Switch – Hackberry Switch 138 kV Line Termination at Cypress Waters 138 kV Switch
ERCOT project 76652 · utility no. M5344
ONCOR
Tier 4
In-Service
Completed tab
138 May 2026
actual 2026-05
Cypress Waters
Dallas County
Cypress Waters

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676652Moved between tabsCurrent-year planned → Completed
October 1, 202676652Status as reportedPlanned → In-Service
February 1, 202664239Moved between tabsFuture → Current-year planned
February 1, 202676652Moved between tabsFuture → Current-year planned
October 1, 202476652Projected in-service dateDec 2025 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first