Cedar Hill Switch
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: CEDAR HILL (DALLAS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Cedar Hill Switch - Webb 345 kV Line Upgrade Cedar Hill Switch - Webb 345 kV Line ERCOT project 109931 · utility no. M4522, M4230 |
ONCOR Tier 1 |
Conceptual Future tab |
345 | Jun 2029 | Cedar Hill Switch to Webb Dallas County |
Cedar Hill Switch, Webb |
| Cedar Hill Switch - Sherry Switch 138 kV Double-Circuit Line Upgrade Cedar Hill Switch - Sherry Switch 138 kV Double-Circuit Line ERCOT project 110679 · utility no. M5246 |
ONCOR Tier 4 |
Conceptual Future tab |
138 | Jun 2032 | Cedar Hill Switch to Sherry Switch Dallas County |
Cedar Hill Switch, Sherry Switch |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 109931 | First listed | on the Future tab |
| July 13, 2026 | 110679 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.