Substation Scout

Wildhorse POD

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of June 1, 2025.

—county as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Adds Capacitor Bank at Wildhorse POD
ERCOT project 92911 · utility no. R8664
ONCOR
Tier 4
Planned
Future tab
138 Dec 2028
actual 2027-05
Wildhorse POD to Wildhorse POD Wildhorse POD

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202692911Projected in-service dateMay 2027 → Dec 2028
June 1, 202592911First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.