Waterport
Named in 3 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of May 12, 2023.
—county as printed
138kV
BPUB, BPUB/BROWNSVILLE PUButility
3projects listed
Also printed as: Waterport Substation
No HIFLD substation record has this name in this county.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This is a new planned substation project BPUB has a planned new substation project that will be between our existing Waterport Substation and STEC's Southmost Substation. ERCOT project 111985 |
BPUB Tier 4 |
Planned Future tab |
138 | Nov 2028 | No terminals printed | Waterport, Southmost |
| New transformer (T1) at BPUB Waterport Substation BPUB new load T1 at bus 59450 ERCOT project 73663 |
BPUB/BROWNSVILLE PUB Tier 4 |
Planned Future tab |
138 | Apr 2027 | Waterport Substation (59450) | Waterport Substation |
| New substation to replace Loma Alta ERCOT project 93831 |
BPUB Tier 3 |
Planned Future tab |
138 | Oct 2028 | Stillman, Waterport, and also future Nimzo Substations to Cipher (Loma Alta) | Stillman, Waterport, and also future Nimzo Substations, Cipher (Loma Alta) |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 111985 | First listed | on the Future tab |
| June 1, 2025 | 73663 | Projected in-service date | Apr 2025 → Apr 2027 |
| June 1, 2025 | 93831 | First listed | on the Future tab |
| June 1, 2024 | 73663 | Projected in-service date | Mar 2024 → Apr 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.