Substation Scout

Stevens Tap

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of June 1, 2024.

—county as printed
69kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lon Hill to Sinton: Bypass Waterworks 69 kV station
Relocate portion of 69 kV line between Odem and Stevens Tap to bypass Waterworks 69 kV station
ERCOT project 80850
AEP TCC
Tier 4
Planned
Future tab
69 Dec 2027 Odem to Stevens Tap
Nueces County
Odem, Stevens Tap

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202680850Projected in-service dateOct 2027 → Dec 2027
February 1, 202680850Projected in-service dateApr 2026 → Oct 2027
October 1, 202580850Moved between tabsCurrent-year planned → Future
October 1, 202580850Projected in-service dateNov 2025 → Apr 2026
June 1, 202580850Moved between tabsFuture → Current-year planned
June 1, 202580850Projected in-service dateMay 2025 → Nov 2025
June 1, 202480850First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.