Substation Scout

Saxet

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of February 1, 2025.

—county as printed
138kV
LCRATSCutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Saxet Substation Addition Phase 2
This PMCR models the phase 2 cut-in of T437 Nueces Bay – Lon Hill with the second Saxet Hard Tap. LCRA TSC will add a temporary Tap on T437
ERCOT project 86043
LCRATSC
Tier 4
Planned
Completed tab
138 Jun 2025
actual 2025-06
No terminals printed Saxet

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202586043Moved between tabsCurrent-year planned → Completed
June 1, 202586043Moved between tabsFuture → Current-year planned
February 1, 202586043Projected in-service dateMay 2025 → Jun 2025
October 1, 202486043First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first