Substation Scout

S-0996 Nockenut

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of July 13, 2026.

—county as printed
345kV
CPS/NOutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install new 345kV transmission loop in conjunction with S-0996 Nockenut switchyard and 1st structure outside new switchyard for Point of Interconnect (POI)
ERCOT project 109933 · utility no. T-0337
CPS/NO
Tier 4
Planned
Future tab
345 Jan 2029 5326 to 51335380
Guadalupe / Wilson County
S-0996 Nockenut

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109933First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.