Red Gulch

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of June 1, 2026.

—county as printed
138kV
PECutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Addition of the Red Gulch 138 kV substation
Addition of Red Gulch station on existing Bertram - Andice transmission line.
ERCOT project 104554
PEC
Tier 4
Planned
Future tab
138 Mar 2030 No terminals printed Red Gulch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026104554First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.