Substation Scout

Reading

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of July 13, 2026.

—county as printed
138kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Flewellen 4th Distribution Transformer Addition and associated upgrades
Upgrade Crabb River Road substation equipment to increase thermal limits on Ckt.09F Reading to Crabb River Road.
ERCOT project 109652D
CNP
Tier 4
Planned
Future tab
138 May 2027 Crabb River Road to Reading
Fort Bend County
Crabb River Road, Reading

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109652DFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this