Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of June 1, 2019.

—county as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Quanah: Rebuild 69 kV Station
Rehab Quanah 69 kV station
ERCOT project 98593 · utility no. TA2018027
AEP TNC
Tier 4
Planned
Future tab
69 Jan 2027 Quanah Quanah

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202698593Moved between tabsCurrent-year planned → Future
October 1, 202698593Projected in-service dateDec 2026 → Jan 2027
February 1, 202698593Moved between tabsFuture → Current-year planned
February 1, 202698593Projected in-service dateFeb 2026 → Dec 2026
October 1, 202598593First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.