Substation Scout

Mitchell

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2026.

—county as printed
69kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Oak Spring Switch - Colorado City Switch 69 kV Line
Rebuild the 18.4-mile Oak Spring - Colorado City 69 kV Line
ERCOT project 110494 · utility no. R8904
ONCOR
Tier 3
Conceptual
Future tab
69 Dec 2030 Nolan to Mitchell Nolan, Mitchell

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110494First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first