MALEZA

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2023.

—county as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Julia CEHE-Owned Sub for Melaza Solar (21INR0220)
Install generator lead from Julia (JUL) CEHE substation to MALEZA/Maleza Solar
ERCOT project 71004B
CNP
Tier 4
In-Service
Future tab
345 Dec 2028
actual 2026-05
Julia to MALEZA
Wharton County
Julia, MALEZA

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202671004BMoved between tabsCurrent-year planned → Future
June 1, 202671004BStatus as reportedPlanned → In-Service
June 1, 202671004BProjected in-service dateMay 2026 → Dec 2028
February 1, 202671004BMoved between tabsFuture → Current-year planned
October 1, 202571004BProjected in-service dateMar 2026 → May 2026
June 1, 202571004BProjected in-service dateOct 2025 → Mar 2026
February 1, 202571004BProjected in-service dateMay 2025 → Oct 2025
October 1, 202471004BProjected in-service dateDec 2024 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.