Named in 2 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of February 1, 2015.

—county as printed
69, 138kV
STECutility
2projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Driscoll- Loyola
Upgrade Driscol-Ricardo-Riviera-Loyola to 795 ACSR
ERCOT project 76786
STEC
Tier 4
Under Construction
Current-year planned tab
69 Dec 2026 Driscoll to Loyola
Nueces County
Driscoll, Loyola
Upgrade Loyola Auto
ERCOT project 76816
STEC
Tier 4
Planned
Future tab
138 Mar 2027 Loyola to Loyola Loyola

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676786Status as reportedPlanned → Under Construction
February 1, 202676786Moved between tabsFuture → Current-year planned
February 1, 202676786Projected in-service dateMay 2028 → Dec 2026
February 1, 202676816Projected in-service dateDec 2026 → Mar 2027
October 1, 202576816Projected in-service dateMay 2026 → Dec 2026
February 1, 202576786Projected in-service dateMay 2026 → May 2028
October 1, 202476816Projected in-service dateDec 2025 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.