Howard

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2025.

—county as printed
345kV
STECutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
STEC Rodgers Large Load Phase 3
-Upgrade CPS Martinez 345/138kV autos 1,2 to 683 MVA -Rebuild CPS Howard to Spruce 345kV to 1580MVA - Rebuild CPS Howard to Braunig to 1457 MVA -Upgrade CPS Hill Country 345/138kV autos 3,4 to 740MVA rating - Rebuild CPS Cachena to Elmcreek to 1250MVA
ERCOT project 110529 · RPG 25RPG046
STEC
Tier 1
Conceptual
Future tab
345 Dec 2030 No terminals printed Howard, Spruce

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110529Projected in-service dateJul 2031 → Dec 2030
July 13, 2026110529First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.