Halsell

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2026.

—county as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Oncor_MW_113288_Halsell_Switch
Establish Halsell 345 kV Switch (POI for Possum Kingdom Solar and Storage)
ERCOT project 113288
ONCOR
Tier 4
Planned
Future tab
345 Sep 2027 No terminals printed Halsell

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026113288First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.