D'Hanis
Named in 2 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2022.
—county as printed
69kV
STECutility
2projects listed
No HIFLD substation record has this name in this county.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| D'Hanis Capacitor addition Add 9.6 MVAR capacitor step at D'Hanis ERCOT project 70371 |
STEC Tier 4 |
Planned Current-year planned tab |
69 | Dec 2026 | D'Hanis | D'Hanis |
| D'Hanis Capacitor 2nd step addition D'Hanis Capacitor 2nd step addition 9.6 MVAR ERCOT project 76123 |
STEC Tier 4 |
Conceptual Future tab |
69 | May 2030 | D'Hanis | D'Hanis |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 70371 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 70371 | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2026 | 76123 | Status as reported | Planned → Conceptual |
| February 1, 2026 | 76123 | Projected in-service date | May 2027 → May 2030 |
| February 1, 2025 | 70371 | Projected in-service date | Dec 2024 → May 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.