Comanche Peak

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of July 13, 2026.

—county as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Comanche Peak Switch - Johnson Switch 345 kV Line
Upgrade Comanche Peak Switch - Johnson Switch 345 kV Line
ERCOT project 110393 · utility no. M5369
ONCOR
Tier 3
Conceptual
Future tab
345 Dec 2030 Comanche Peak to Johnson Comanche Peak, Johnson

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110393First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.