Substation Scout

Coleto Creek

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of July 13, 2026.

—county as printed
345kV
STECutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
STEC Mesquite Large Load Project Phase 5
Upgrade 5068 CACHENA - 5133 ELMCREEK 345-kV Line CKT 2 Upgrade 5068 CACHENA - 5323 OLD_HCKRY_5 345-kV Line CKT 2 Upgrade 5133 ELMCREEK - 5380 SHAULA 345-kV Line CKT 1 Upgrade 5915 SO_TEX__345A - 8676 STATIC7A 345-kV Line CKT 1 Upgrade 8012 PALADIO7A - 8606 GODDARD7A 345-kV Line CKT 1 Upgrade 8249 ANGSTRM7A - 8676 STATIC7A 345-kV Line CKT 1 Upgrade 8249 ANGSTRM7A - 8956 WHITEPT7A 345-kV Line CKT 1 …
ERCOT project 110876
STEC
Tier 2
Conceptual
Future tab
345 May 2031 No terminals printed Coleto Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110876First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.