Castroville

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of May 12, 2023.

—county as printed
138kV
STECutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Upgrade Castroville sub to 138kV” — project 71935, as the utility reported it

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Hondo Creek to Castroville to 138kV
Upgrade Castroville sub to 138kV and line from Hondo creek to Castroville
ERCOT project 71935 · RPG 22RPG022
STEC
Tier 2
In-Service
Completed tab
138 Sep 2025
actual 2025-12
No terminals printed Castroville

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202671935Moved between tabsCurrent-year planned → Completed
October 1, 202671935Status as reportedPlanned → In-Service
June 1, 202571935Moved between tabsFuture → Current-year planned
February 1, 202571935Projected in-service dateFeb 2025 → Sep 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.