Substation Scout

Odysseus

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Coke County. First named in the release with data as of May 12, 2023.

Cokecounty as printed
345kV
AEP TNCutility
1projects listed

Described as new. The quoted wording calls this substation new. “Odysseus: Build new 345 kV station” — project 73408 title, as the utility reported it

Reported complete. Project 73408 is on the Completed tab (actual in-service 2025-12), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Coke, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Location

Coke County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TPIT lists 73408 on the Completed tab: in service, actual date 2025-12.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, projects 73408 (release 2026-10) · AEP Texas construction progress report (North Division), PUCT Project 57477 item 149 (2025-05-15), North Division, Odysseus entries · OpenStreetMap: Coke County power features (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Odysseus: Build new 345 kV station
Interconnect Ulysses Solar to the Odysseus 345 kV Station on the Bluff Creek to SA Red Creek 345 kV line
ERCOT project 73408
AEP TNC
Tier 4
Planned
Completed tab
345 Jan 2026
actual 2025-12
Odysseus
Coke County
Odysseus

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202673408Moved between tabsCurrent-year planned → Completed
February 1, 202673408Projected in-service dateDec 2025 → Jan 2026
October 1, 202573408Projected in-service dateMay 2025 → Dec 2025
June 1, 202573408Moved between tabsFuture → Current-year planned
June 1, 202473408Projected in-service dateOct 2024 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.