Odysseus
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Coke County. First named in the release with data as of May 12, 2023.
Described as new. The quoted wording calls this substation new. “Odysseus: Build new 345 kV station” — project 73408 title, as the utility reported it
Reported complete. Project 73408 is on the Completed tab (actual in-service 2025-12), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Coke, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.
Location
Coke County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: TPIT lists 73408 on the Completed tab: in service, actual date 2025-12.
Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, projects 73408 (release 2026-10) · AEP Texas construction progress report (North Division), PUCT Project 57477 item 149 (2025-05-15), North Division, Odysseus entries · OpenStreetMap: Coke County power features (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Odysseus: Build new 345 kV station Interconnect Ulysses Solar to the Odysseus 345 kV Station on the Bluff Creek to SA Red Creek 345 kV line ERCOT project 73408 |
AEP TNC Tier 4 |
Planned Completed tab |
345 | Jan 2026 actual 2025-12 |
Odysseus Coke County |
Odysseus |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 73408 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 73408 | Projected in-service date | Dec 2025 → Jan 2026 |
| October 1, 2025 | 73408 | Projected in-service date | May 2025 → Dec 2025 |
| June 1, 2025 | 73408 | Moved between tabs | Future → Current-year planned |
| June 1, 2024 | 73408 | Projected in-service date | Oct 2024 → May 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.