Substation Scout

Tesla

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Childress County. First named in the release with data as of June 1, 2019.

Childresscounty as printed
345kV
AEP TNC/ETT, ETTutility
2projects listed

Expansion at an existing substation: named load connected. The quoted wording describes a named load being connected at this substation. “Interconnect the Lancium load to the existing Tesla 345 kV station” — project 81576, as the utility reported it

A HIFLD substation record has the same name and county: TESLA (CHILDRESS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Childress, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Tesla: Build 345 kV terminal
Interconnect Misae II solar farm at Tesla
ERCOT project 49574 · utility no. 2785
ETT
Tier 4
In-Service
Completed tab
345 Jun 2025
actual 2025-06
Tesla
Childress County
Tesla
Tesla: Construct New 345 kV Terminal
Interconnect the Lancium load to the existing Tesla 345 kV station
ERCOT project 81576
AEP TNC/ETT
Tier 4
Planned
Current-year planned tab
345 Nov 2026 Tesla
Childress County
Tesla

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202649574Moved between tabsCurrent-year planned → Completed
February 1, 202649574Status as reportedUnder Construction → In-Service
February 1, 202681576Moved between tabsFuture → Current-year planned
February 1, 202681576Projected in-service dateOct 2026 → Nov 2026
October 1, 202549574Projected in-service dateMay 2025 → Jun 2025
October 1, 202581576Projected in-service dateApr 2027 → Oct 2026
June 1, 202549574Moved between tabsFuture → Current-year planned
February 1, 202549574Status as reportedPlanned → Under Construction
February 1, 202549574Projected in-service dateOct 2024 → May 2025
October 1, 202481576Status as reportedConceptual → Planned
October 1, 202481576Projected in-service dateDec 2026 → Apr 2027
June 1, 202481576First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.