Salvare

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Childress County. First named in the release with data as of February 1, 2022.

Childresscounty as printed
345kV
ETTutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Childress, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Salvare: Install New 345 kV Feed
Install 2nd POI for IRIS Data center
ERCOT project 104448 · utility no. TP2026040
ETT
Tier 4
Planned
Future tab
345 Feb 2028 Salvare
Childress County
Salvare
Salvare: Install New 345 kV Capacitor Bank
Install a new capacitor bank at the Salvare 345 kV station
ERCOT project 90002 · utility no. TP2024109
ETT
Tier 4
Planned
Future tab
345 Nov 2028 Salvare
Childress County
Salvare

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026104448Projected in-service dateOct 2028 → Feb 2028
July 13, 202690002Projected in-service dateFeb 2028 → Nov 2028
June 1, 2026104448First listedon the Future tab
February 1, 202690002Projected in-service dateMar 2027 → Feb 2028
October 1, 202590002Projected in-service dateDec 2026 → Mar 2027
June 1, 202590002Projected in-service dateMay 2026 → Dec 2026
February 1, 202590002First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.