Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Borden County. First named in the release with data as of February 1, 2015.

Bordencounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Borden, TX: ERCOT queue, 17 active of 19 · SPP queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Stoplight Switch (fka Bluff Creek) - Willow Valley Switch 138 kV Line
Rebuild the existing 19.9-mile Stoplight Switch (fka Bluff Creek) - Willow Valley Switch 138 kV Line
ERCOT project 110593 · utility no. R8840
ONCOR
Tier 4
Conceptual
Future tab
138 Jun 2032 Stoplight Switch (fka Bluff Creek) to Willow Valley Switch
Scurry / Borden County
Stoplight Switch (fka Bluff Creek), Willow Valley Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110593First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.