Substation Scout

Massey Lake 138 kV Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Anderson County. First named in the release with data as of October 1, 2026.

Andersoncounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Anderson, TX: ERCOT queue, 9 active of 9. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Massey Lake 138 kV Switch
ERCOT project 111796 · utility no. R6400
ONCOR
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Massey Lake 138 kV Switch to Massey Lake 138 kV Switch
Anderson County
Massey Lake 138 kV Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026111796First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first