0 active projects
totaling 0 MW in the SPP queue, plus 2 with terminal status (shown grayed).
2 SPP queue filings name Whitlock Substation as the point of interconnection, all in Potter County, SD.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2020-093
Not reported
230
150
Solar
Withdrawn
GEN-2023-130
Not reported
230
96
Hybrid
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.