Substation Scout

West Gardner substation interconnection queue

2 active projects totaling 628.4 MW in the SPP queue, plus 2 with terminal status (shown grayed).

4 SPP queue filings name West Gardner as the point of interconnection, all in KS.

2active projects
628.4active MW
4total filed
Queue IDProjectkVMWResourceStatus
GEN-2017-195 Not reported 345 500.4 Solar Active
GEN-2016-157 Not reported 345 252 Wind Withdrawn
GEN-2016-158 Not reported 345 252 Wind Withdrawn
GEN-2017-196 Not reported 345 128 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.