Tenaska - Crockett substation interconnection queue

0 active projects totaling 0 MW in the SPP queue, plus 3 with terminal status (shown grayed).

3 SPP queue filings name Tenaska - Crockett as the point of interconnection, all in Nacogdoches County, TX.

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2014-018 Not reported 345 756.8 Gas Withdrawn
GEN-2014-017 Not reported 345 477 Gas Withdrawn
GEN-2014-016 Not reported 345 227 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.