Tap of Oklaunion to Lawton Eastside Transmission Line substation interconnection queue

0 active projects totaling 0 MW in the SPP queue, plus 3 with terminal status (shown grayed).

3 SPP queue filings name Tap of Oklaunion to Lawton Eastside Transmission Line as the point of interconnection, all in Tillman County, OK.

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-107 Not reported 345 400 Solar Withdrawn
GEN-2022-105 Not reported 345 300 Solar Withdrawn
GEN-2022-106 Not reported 345 300 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.