Substation Scout

Tap of Neosho - LaCygne Line substation interconnection queue

2 active projects totaling 500 MW in the SPP queue.

2 SPP queue filings name Tap of Neosho - LaCygne Line as the point of interconnection, all in Bourbon County, KS.

2active projects
500active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-013 Not reported 345 300 Solar Active
GEN-2022-024 Not reported 345 200 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first