Portales Substation substation interconnection queue

1 active project totaling 199.5 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2 SPP queue filings name Portales Substation as the point of interconnection, all in Roosevelt County, NM.

1active projects
199.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-092 Not reported 115 199.5 Battery Active
GEN-2024-354 Not reported 115 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.